top of page

Oil Pipeline

Oil & Gas

Fast-track detail engineering for a critical 16" pipeline in a high-risk brownfield refinery, utilizing Point Cloud and BIM to minimize on-site hot work and achieve zero on-site reworks

Key Information

Pipe size

Piping 250m@16"

Steel structure

10 ton

Location

Montevideo, Uruguay

Date

2025

Surfista al atardecer

Our  Company  Scope

  • Modeling & integration: Discipline coordination via BIM (ISO 19650). Existing facility survey using Point Cloud and 3D modeling.


  • Detail engineering: Development of piping, structural, electrical, and civil engineering under ASME, API, and AISC standards. Electrical panels designed with ATEX certification.


  • Deliverable strategy: Fast-track partial deliveries to anticipate procurement and fabrication, ensuring project deadlines were met.

Project Overview

An important client required the detail engineering for the urgent construction of a critical 16” pipeline section (main crude oil intake) for an important refinery. 


As a Brownfield project in a high-risk operational environment, the client’s need focused on a high-precision technical solution to allow for pre-fabrication and minimize on-site hot work for safety reasons.

Services involved

Project Management

Design

Disciplines involved

Design Management

Instrumentation & Control

Electrical

Mechanical & Process

Civil, Structural & Architecture

Core project team

Luis Carozo

Mechanical Engineer

Diego Ingold

Civil

Matilde Estefan

Electrical Engineer

Lucía Cetrangolo

Mechanical Engineer

Valentín Vanerio

Civil Engineer

Explore More Projects